SUMMARY FOR MAJARDAH UPGRADE PUNCH CLOSURE (AS OF 30-July-2024)

PAC Punch Items Summary

SM1-WTS

Sr. No DISCIPLINE OPEN APPROVED (CLOSED) UNDER REVIEW (POYRY) REJECTED GRAND TOTAL COMPLETED %
1 GENERAL 76 0 0 0 76 0%
2 CIVIL - STATION 2168 1024 15 182 3389 30%
3 CIVIL - PIPELINE 4650 941 0 120 5711 16%
4 MECHANICAL - STATION 89 1065 410 200 1764 60%
5 MECHANICAL - PIPELINE 1485 316 18 10 1829 17%
6 ELECTRICAL 1489 115 64 186 1854 6%
7 I & C 712 584 86 194 1576 37%
TOTAL 10669 4045 593 892 16199 25%